About SPC | Site Map | E-News Sign-up Search:  
Southern Pine by Design logo
Southern Pine Home





  Southern Pine Flooring: Subfloor Installation

Figure 3 Moisture Barrier A suitable moisture barrier and subfloor nailing base (over concrete slab or wood joists) must be installed to provide adequate protection and support for the flooring.

Remember: the nailing base should be in place prior to flooring delivery and the acclimation period.

Recommended Moisture Barriers

Two types of moisture barrier material are recommended beneath Southern Pine flooring:

Polyethylene: A 6-mil thickness is preferred; 4-mil is acceptable. The 6-mil material has a perm rating of 0.08. A perm rating below 1.0 for polyethylene is required to retard moisture.
Roofing felt paper: Two layers of 15 lb. paper, or one layer of 30 lb. paper.

Subfloors Over Concrete

Figure 4 Screed Method Concrete is a porous material that allows the migration of water vapor from the ground into the structure. Concrete hardens over time, but it can still contain water up to 60 days after installation, and sometimes longer.

Proper construction practices require that a vapor barrier be installed prior to the concrete installation to reduce the moisture absorption process. Southern Pine flooring can be installed on concrete subfloors, either on or above grade.

Once the concrete is determined to be dry, a moisture barrier and nailing base can be installed. Refer to Figures 5 and 6.

To create a nailing base over concrete, two methods can be used: either a layer of dimension lumber strips (called "screeds") or a layer of plywood. When using the screed method, it is recommended that 2x4 material be used, cut into lengths varying from 18" to 48".

Screeds must be dry. If pressure-treated screeds are used, they MUST be kiln dried after treatment (KDAT).

Figure 5 Subfloor Detail Clean the concrete, removing any oils or other foreign material. For a screed nailing base, apply a cold cutback asphalt adhesive mastic to the surface at a spread rate of 35 square feet per gallon and embed screeds on the wide face, 12" on center, perpendicular to the direction the flooring will lay. End walls should have a continuous screed run. A 3/4" gap should be left between walls and screed ends. Apply the moisture barrier, overlapping sides 4" and touching end walls.

For a plywood nailing base over concrete, spread cold cutback mastic at a 50 sq.ft. per gallon rate. Allow two hours setting time; lay the moisture barrier with a 4" side overlap and touching the end walls. When using a 15 lb. felt moisture barrier, an additional layer of a cold cutback asphalt adhesive mastic and felt is applied. Stagger felt seams to prevent direct alignment with the first layer. Laying plywood diagonally to the direction of the flooring will offset plywood joints with floor nailing.

Start with a 4'x4' section every other course, staggering plywood joints. Allow a gap of 1/4" to 1/2" between panels, and a 3/4" gap at walls. Use at least 9 nails per panel, nailing outward from the center, flattening the panels. Refer to Figures 5 and 6.

Figure 6 Plywood Nailing Base Over Concrete Slab

Concrete Condition A,B,C Concrete Condition Check Concrete Condition Check

If a moisture meter is unavailable to check the condition of the concrete, a sheet of polyethylene cut to 24"x24" will reveal the slab’s moisture condition. Secure the polyethylene to the concrete with duct tape (A), forming an air-sealing bond. Wait 24 hours. If condensation develops between the concrete and the polyethylene sheet (B), do not install flooring; the concrete is too wet for wood flooring and must be permitted more time to cure. If the structure is several months old and the concrete has cured, yet the poly test still reveals condensation formation, inspect the site for moisture problems caused by improper drainage. Slower percolating soils do not drain as efficiently, causing hydrostatic water pressure. Correct a drainage problem by upgrading or adding drain tiles at the foundation footings.

A similar moisture test for concrete is the "rubber mat" test. Lay a rubber mat flat on the concrete floor. Place a concrete block, tool box or other heavy object on top of the mat, (C) trapping any air from escaping. After 24 hours, lift the mat. If the concrete is darker beneath the mat on a lighter background concrete, then moisture has formed, indicating the concrete is too wet for flooring. Dark concrete surfaces tend to camouflage wetness; therefore, use the rubber mat test on light-colored concrete surfaces for best results.

Until the concrete is noticeably dry on the underside of the polyethylene or the rubber mat, do not install the subfloor. Should wet concrete still be evident, fans and dehumidifiers will improve air circulation and lower the humidity.

When the concrete is determined to be dry, a moisture barrier and nailing base can be installed.

Subfloors Over Wood Joists

For installation of flooring over wood floor joists, a subfloor nailing base consisting of a minimum 5/8" plywood or 3/4" oriented-strand-board (OSB) is required. Lay the subfloor panels perpendicular to the joists.

Figure 7 Plywood Subfloor Over Wood Joists

Use of a caulk-type construction adhesive between plywood subfloor and joists provides additional anchoring support. Starting with a single 4'x4' panel in one corner, alternating courses of 4'x8' panels are to be staggered, offsetting the end seams. An 1/8" space between panels allows for panel expansion and prevents panel squeaks. Position all seams between panels directly over the joists. A 6d screw or ring-shank nail is recommended every 6" for fastening panels to floor joists.

Lay the moisture barrier atop the plywood, overlapping edges 4" and touching all walls. If 15 lb. felt is chosen, stagger the edges of the second layer in relation to the first.

Check local building codes to verify subfloor requirements for your area.

Southern Pine Flooring

Previous   Next


Southern Pine Council™
Copyright © 1995-2008. All rights reserved.
Legal Disclaimer